ITAC Assessment: GT0495
ITAC logo
ITAC Assessment: GT0495
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Welded Steel Tubing
NAICS
n/a
SIC 3317: Steel Pipe and Tubes
Sales Range $5
M
to 10
M
# of Employees 61
Plant Area 50,000
ft2
Annual Production 36,000
ton
Production Hrs. Annual 7,056
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $291,977 4,698,124
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,690 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,470

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,270 $6,520 $2,270
36,635
kWh
02 2.7135: Install occupancy sensors $320 $500 $320
4,982
kWh
03 2.4133: Use most efficient type of electric motors $4,080 $14,170 $4,080
65,651
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,630 $5,800 $2,630
42,204
kWh
05 2.2694: Use highest temperature for chilling or cold storage $1,390 $500 $1,390
22,567
kWh
TOTAL RECOMMENDED $10,690 $27,490 $10,690
172,039
kWh
TOTAL IMPLEMENTED $5,470 $14,670 $5,470
88,218
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs