| Assessment Year | 1992 |
|---|---|
| Principal Product | PROPPANTS |
| NAICS |
n/a
|
| SIC | 2911: Petroleum Refining |
| Sales Range | $10 M to 50M |
| # of Employees | 27 |
| Plant Area |
n/a
|
| Annual Production | 76,000,000
lb
|
| Production Hrs. Annual | 8,500
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $284,999 | 5,573,857 |
kWh
|
$0.051 |
| Natural Gas | $1,031,902 | 293,895 |
MMBtu
|
$3.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $158,248 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $158,248 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2424: Use heat in flue gases to preheat products or materials | $58,750 | $22,000 | - |
$58,750
-
MMBtu
|
- | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $53,900 | $56,000 | - |
$53,900
-
MMBtu
|
- | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,247 | $500 | - |
$7,247
-
MMBtu
|
- | |
| 04 | 2.2511: Insulate bare equipment | $35,964 | $13,262 | - |
$35,964
-
MMBtu
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,747 | $23,600 |
$1,747
159,144
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $538 | - |
$538
48,945
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $102 | $1,210 |
$154
14,068
kWh
|
- | $(-52.0) | |
| TOTAL RECOMMENDED | $158,248 | $116,572 |
$2,439
222,157
kWh
|
$155,861
-
MMBtu
|
$(-52.0) | ||
| TOTAL IMPLEMENTED | $158,248 | $116,572 |
$2,439
222,157
kWh
|
$155,861
-
MMBtu
|
$(-52.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs