| Assessment Year | 1992 |
|---|---|
| Principal Product | BOUND BOOKS & JOURNALS |
| NAICS |
n/a
|
| SIC | 2731: Books: Publishing, or Publishing and Printing |
| Sales Range | $5 M to 10M |
| # of Employees | 95 |
| Plant Area |
n/a
|
| Annual Production | 1,800
ton
|
| Production Hrs. Annual | 4,240
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $115,702 | 1,426,143 |
kWh
|
$0.081 |
| Natural Gas | $2,364 | 360 |
MMBtu
|
$6.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,749 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,749 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $934 | $150 |
$934
11,430
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,100 | $8,510 |
$2,271
28,136
kWh
|
- | $(-171.0) | |
| 03 | 2.7122: Disconnect ballasts | $136 | $50 |
$136
1,758
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $465 | $6,040 |
$1,363
16,706
kWh
|
- | $(-898.0) | |
| 05 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $85 | - | - |
$85
-
MMBtu
|
- | |
| 06 | 2.7492: Use proper thickness of insulation on building envelope | $3,920 | $18,300 |
$2,538
31,360
kWh
|
$1,382
-
MMBtu
|
- | |
| 07 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $109 | - |
$109
1,465
kWh
|
- | - | |
| TOTAL RECOMMENDED | $7,749 | $33,050 |
$7,351
90,855
kWh
|
$1,467
-
MMBtu
|
$(-1,069.0) | ||
| TOTAL IMPLEMENTED | $7,749 | $33,050 |
$7,351
90,855
kWh
|
$1,467
-
MMBtu
|
$(-1,069.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs