Assessment Year | 1992 |
---|---|
Principal Product | BOUND BOOKS & JOURNALS |
NAICS |
n/a
|
SIC | 2731: Books: Publishing, or Publishing and Printing |
Sales Range | $5 M to 10M |
# of Employees | 95 |
Plant Area |
n/a
|
Annual Production | 1,800
ton
|
Production Hrs. Annual | 4,240
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $115,702 | 1,426,143 |
kWh
|
$0.081 |
Natural Gas | $2,364 | 360 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,749 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,749 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $934 | $150 |
$934
11,430
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,100 | $8,510 |
$2,271
28,136
kWh
|
- | $(-171.0) | |
03 | 2.7122: Disconnect ballasts | $136 | $50 |
$136
1,758
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $465 | $6,040 |
$1,363
16,706
kWh
|
- | $(-898.0) | |
05 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $85 | - | - |
$85
-
MMBtu
|
- | |
06 | 2.7492: Use proper thickness of insulation on building envelope | $3,920 | $18,300 |
$2,538
31,360
kWh
|
$1,382
-
MMBtu
|
- | |
07 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $109 | - |
$109
1,465
kWh
|
- | - | |
TOTAL RECOMMENDED | $7,749 | $33,050 |
$7,351
90,855
kWh
|
$1,467
-
MMBtu
|
$(-1,069.0) | ||
TOTAL IMPLEMENTED | $7,749 | $33,050 |
$7,351
90,855
kWh
|
$1,467
-
MMBtu
|
$(-1,069.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs