Assessment Year | 1991 |
---|---|
Principal Product | DIMENSION STONE |
NAICS |
n/a
|
SIC | 3281: Cut Stone and Stone Products |
Sales Range | $10 M to 50M |
# of Employees | 72 |
Plant Area |
n/a
|
Annual Production | 41,400
ton
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $531,322 | 6,179,953 |
kWh
|
$0.086 |
Natural Gas | $43,524 | 7,439 |
MMBtu
|
$5.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,921 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,921 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $500 | - | - |
$800
-
MMBtu
|
$(-300.0) | |
02 | 2.2121: Increase amount of condensate returned | $960 | - | - |
$960
-
MMBtu
|
- | |
03 | 2.2122: Install / repair insulation on condensate lines | $158 | $289 | - |
$158
-
MMBtu
|
- | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $37,560 | - |
$37,560
-
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $183 | - |
$238
2,931
kWh
|
- | $(-55.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,110 | $3,441 |
$3,110
38,980
kWh
|
- | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,900 | $4,800 |
$17,900
223,916
kWh
|
- | - | |
08 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $6,550 | $500 |
$6,550
81,770
kWh
|
- | - | |
TOTAL RECOMMENDED | $66,921 | $9,030 |
$65,358
347,597
kWh
|
$1,918
-
MMBtu
|
$(-355.0) | ||
TOTAL IMPLEMENTED | $66,921 | $9,030 |
$65,358
347,597
kWh
|
$1,918
-
MMBtu
|
$(-355.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs