| Assessment Year | 1990 |
|---|---|
| Principal Product | ATHLETIC SOCKS |
| NAICS |
n/a
|
| SIC | 2252: Hosiery, Not Elsewhere Classified |
| Sales Range | n/a |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 9,000,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $37,712 | 422,626 |
kWh
|
$0.089 |
| Natural Gas | $37,880 | 6,709 |
MMBtu
|
$5.65 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,470 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,400 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $621 | $122 |
$621
7,034
kWh
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $650 | $450 | - |
$650
-
MMBtu
|
|
| 03 | 2.4133: Use most efficient type of electric motors | $129 | $703 |
$129
1,465
kWh
|
- | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,190 | $73,850 |
$20,685
231,829
kWh
|
$(-5,495.0)
-
MMBtu
|
|
| 05 | 2.2136: Install / repair insulation on steam lines | $2,170 | $1,120 | - |
$2,170
-
MMBtu
|
|
| 06 | 2.2511: Insulate bare equipment | $710 | $850 | - |
$710
-
MMBtu
|
|
| TOTAL RECOMMENDED | $19,470 | $77,095 |
$21,435
240,328
kWh
|
$(-1,965.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,400 | $1,275 |
$750
8,499
kWh
|
$650
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs