ITAC Assessment: GT0408
ITAC logo
ITAC Assessment: GT0408
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product STAINLESS FIXTURES
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $5
M
to 10
M
# of Employees 70
Plant Area
n/a
Annual Production 805,000
lb
Production Hrs. Annual 4,375
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,758 786,049
kWh
Natural Gas $16,654 3,012
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,710

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7141: Lower light fixtures in high ceiling areas $6,500 $5,860 $6,500
109,320
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,900 $3,771 $1,900
31,946
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $810 - $810
13,482
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $37 - $37
586
kWh
05 2.4133: Use most efficient type of electric motors $32 $57 $32
586
kWh
TOTAL RECOMMENDED $9,279 $9,688 $9,279
155,920
kWh
TOTAL IMPLEMENTED $2,710 $3,771 $2,710
45,428
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs