ITAC Assessment: GT0407
ITAC logo
ITAC Assessment: GT0407
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product CABINET LOCKS
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 16,000,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $263,772 4,745,018
kWh
Natural Gas $40,596 7,807
MMBtu
Fuel Oil #2 $22,054 5,460
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,721 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,233

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,233 $464 $1,233
22,274
kWh
- -
02 2.4133: Use most efficient type of electric motors $198 $422 $198
3,517
kWh
- -
03 2.1331: Burn a less expensive grade of fuel $6,760 - - $29,790
-
MMBtu
$(-23,030.0)
-
MMBtu
04 2.1243: Use heat from boiler blowdown to preheat boiler feed water $300 $3,000 - - $300
-
MMBtu
05 2.7226: Use computer programs to optimize hvac performance $940 - $940
16,999
kWh
- -
06 2.2621: Modify refrigeration system to operate at a lower pressure $290 $1,200 $290
8,206
kWh
- -
TOTAL RECOMMENDED $9,721 $5,086 $2,661
50,996
kWh
$29,790
-
MMBtu
$(-22,730.0)
-
MMBtu
TOTAL IMPLEMENTED $9,233 $3,464 $2,173
39,273
kWh
$29,790
-
MMBtu
$(-22,730.0)
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs