| Assessment Year | 1989 |
|---|---|
| Principal Product | TUFTED CARPET |
| NAICS |
n/a
|
| SIC | 2273: Carpets and Rugs |
| Sales Range | $1 M to 5M |
| # of Employees | 616 |
| Plant Area |
n/a
|
| Annual Production | 25,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $721,333 | 13,640,094 |
kWh
|
$0.053 |
| Natural Gas | $185,465 | 54,786 |
MMBtu
|
$3.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $36,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,653 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,350 | $2,699 |
$20,350
384,525
kWh
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $957 | $790 |
$957
18,171
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,113 | - |
$2,113
39,859
kWh
|
- | - | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $904 | $10,000 | - |
$904
-
MMBtu
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $739 | - | - |
$1,039
-
MMBtu
|
$(-300.0) | |
| 06 | 2.2136: Install / repair insulation on steam lines | $550 | $534 | - |
$550
-
MMBtu
|
- | |
| 07 | 2.2163: Use minimum steam operating pressure | $933 | - | - |
$933
-
MMBtu
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,494 | $3,000 | - |
$9,494
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $36,040 | $17,023 |
$23,420
442,555
kWh
|
$12,920
-
MMBtu
|
$(-300.0) | ||
| TOTAL IMPLEMENTED | $33,653 | $6,489 |
$23,420
442,555
kWh
|
$10,533
-
MMBtu
|
$(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs