| Assessment Year | 1988 |
|---|---|
| Principal Product | PORTLAND CEMENT |
| NAICS |
n/a
|
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $10 M to 50M |
| # of Employees | 136 |
| Plant Area |
n/a
|
| Annual Production | 967,680
ton
|
| Production Hrs. Annual | 8,064
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $3,459,188 | 86,718,934 |
kWh
|
$0.040 |
| Natural Gas | $404,507 | 100,057 |
MMBtu
|
$4.04 |
| Coal | $2,358,739 | 1,976,775 |
MMBtu
|
$1.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $38,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,420 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $189 | $1,045 |
$189
4,689
kWh
|
|
| 02 | 2.4133: Use most efficient type of electric motors | $7,420 | $6,873 |
$7,420
186,108
kWh
|
|
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $31,186 | - |
$31,186
779,601
kWh
|
|
| TOTAL RECOMMENDED | $38,795 | $7,918 |
$38,795
970,398
kWh
|
||
| TOTAL IMPLEMENTED | $7,420 | $6,873 |
$7,420
186,108
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs