ITAC Assessment: GT0347
ITAC logo
ITAC Assessment: GT0347
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product MOWER BLADES, SPRINGS
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $1
M
to 5
M
# of Employees 42
Plant Area
n/a
Annual Production 8,200,000
lb
Production Hrs. Annual 5,200
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $171,996 2,657,972
kWh
Natural Gas $179,754 56,584
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,825 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,375

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $620 $100 $620
24,033
kWh
-
02 2.2414: Use waste heat from hot flue gases to preheat $44,370 $88,000 - $44,370
-
MMBtu
03 2.4133: Use most efficient type of electric motors $305 $537 $305
4,689
kWh
-
04 2.2531: Re-size charging openings or add movable cover or door $12,420 $1,600 - $12,420
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $11,080 $27,160 $11,080
209,261
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $860 $947 $860
16,413
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $170 $250 $170
3,224
kWh
-
08 2.3131: Reschedule plant operations or reduce load to avoid peaks $43,000 $1,300 $43,000
-
kWh
-
TOTAL RECOMMENDED $112,825 $119,894 $56,035
257,620
kWh
$56,790
-
MMBtu
TOTAL IMPLEMENTED $14,375 $3,434 $1,955
48,359
kWh
$12,420
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs