Assessment Year | 1988 |
---|---|
Principal Product | MEN'S COATS |
NAICS |
n/a
|
SIC | 2311: Men's and Boys' Suits, Coats, and Overcoats |
Sales Range | $10 M to 50M |
# of Employees | 240 |
Plant Area |
n/a
|
Annual Production | 1,020,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $162,265 | 2,135,111 |
kWh
|
$0.076 |
Natural Gas | $21,971 | 3,899 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,070 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,120 | $28,140 |
$12,120
159,437
kWh
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $400 | $180 |
$400
5,275
kWh
|
- | - | |
03 | 2.2136: Install / repair insulation on steam lines | $640 | $425 | - |
$640
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,060 | $40 |
$1,060
14,068
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,366 | - |
$4,366
57,444
kWh
|
- | - | |
06 | 2.7226: Use computer programs to optimize hvac performance | $3,450 | $2,750 |
$3,450
76,495
kWh
|
- | - | |
07 | 2.7291: Reschedule and rearrange multiple-source heating systems | $4,034 | $1,000 | - |
$10,990
-
MMBtu
|
$(-6,956.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $26,070 | $32,535 |
$21,396
312,719
kWh
|
$11,630
-
MMBtu
|
$(-6,956.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,220 | $28,785 |
$13,580
178,780
kWh
|
$640
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs