ITAC Assessment: GT0309
ITAC logo
ITAC Assessment: GT0309
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product MOLDED AUTOMOTIVE TRIM
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 1,400,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $480,432 9,949,883
kWh
Natural Gas $448,619 94,166
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $65,765 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $65,765

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $2,070 $500 $2,070
42,790
kWh
-
02 2.2444: Use hot process fluids to preheat incoming process fluids $15,500 $3,500 - $15,500
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $21,100 $6,000 - $21,100
-
MMBtu
04 2.2414: Use waste heat from hot flue gases to preheat $20,500 $95,000 - $20,500
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,010 $8,940 $5,010
103,751
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $300 $150 $300
6,155
kWh
-
07 2.4133: Use most efficient type of electric motors $1,285 $2,056 $1,285
26,377
kWh
-
TOTAL RECOMMENDED $65,765 $116,146 $8,665
179,073
kWh
$57,100
-
MMBtu
TOTAL IMPLEMENTED $65,765 $116,146 $8,665
179,073
kWh
$57,100
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs