ITAC Assessment: GT0303
ITAC logo
ITAC Assessment: GT0303
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product MILK
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $1
M
to 5
M
# of Employees 21
Plant Area
n/a
Annual Production 5,500
Tgal
Production Hrs. Annual 1,872
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,179 2,191,970
kWh
Natural Gas $81,603 13,730
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,367 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2447: Heat water with exhaust heat $1,449 $8,200 - $1,449
-
MMBtu
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,383 $3,465 $4,383
76,788
kWh
-
03 2.4133: Use most efficient type of electric motors $535 $722 $535
9,379
kWh
-
TOTAL RECOMMENDED $6,367 $12,387 $4,918
86,167
kWh
$1,449
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs