ITAC Assessment: GT0300
ITAC logo
ITAC Assessment: GT0300
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product YARN
NAICS
n/a
SIC 2281: Yarn Spinning Mills
Sales Range $10
M
to 50
M
# of Employees 204
Plant Area
n/a
Annual Production 5,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $401,800 7,363,130
kWh
Natural Gas $174,492 40,059
MMBtu
Fuel Oil #2 $5,108 841
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $165,729 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $165,729

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.4133: Use most efficient type of electric motors $1,458 $2,802 $1,458
53,341
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,023 $9,962 $3,023
110,785
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,822 $6,020 $1,822
66,823
kWh
- -
04 2.2212: Use minimum safe oven ventilation $8,666 - $6,630
242,966
kWh
$2,036
-
MMBtu
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,079 - $1,079
39,566
kWh
- -
06 2.1333: Convert combustion equipment to burn oil $149,681 $2,000 - $144,573
-
MMBtu
$5,108
-
MMBtu
TOTAL RECOMMENDED $165,729 $20,784 $14,012
513,481
kWh
$146,609
-
MMBtu
$5,108
-
MMBtu
TOTAL IMPLEMENTED $165,729 $20,784 $14,012
513,481
kWh
$146,609
-
MMBtu
$5,108
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs