Assessment Year | 1986 |
---|---|
Principal Product | CARPET YARN |
NAICS |
n/a
|
SIC | 2281: Yarn Spinning Mills |
Sales Range | $10 M to 50M |
# of Employees | 312 |
Plant Area |
n/a
|
Annual Production | 14,300,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $599,630 | 12,281,067 |
kWh
|
$0.049 |
Natural Gas | $207,496 | 50,487 |
MMBtu
|
$4.11 |
Fuel Oil #2 | $11,001 | 1,793 |
MMBtu
|
$6.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $272,735 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $225,497 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $4,038 | $4,850 |
$4,038
82,649
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,160 | $23,760 |
$12,160
247,948
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,670 | $4,860 |
$2,670
54,513
kWh
|
- | - | |
04 | 2.2711: Utilize outside air instead of conditioned air for drying | $35,600 | - |
$35,600
725,967
kWh
|
- | - | |
05 | 2.7291: Reschedule and rearrange multiple-source heating systems | $196,997 | - | - |
$190,847
-
MMBtu
|
$6,150
-
MMBtu
|
|
06 | 2.1111: Control pressure on steamer operations | $7,600 | $2,280 | - |
$7,600
-
MMBtu
|
- | |
07 | 2.4312: Improve lubrication practices | $13,670 | - |
$13,670
279,015
kWh
|
- | - | |
TOTAL RECOMMENDED | $272,735 | $35,750 |
$68,138
1,390,092
kWh
|
$198,447
-
MMBtu
|
$6,150
-
MMBtu
|
||
TOTAL IMPLEMENTED | $225,497 | $28,620 |
$28,500
581,476
kWh
|
$190,847
-
MMBtu
|
$6,150
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs