ITAC Assessment: GT0281
ITAC logo
ITAC Assessment: GT0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product CARPET YARN
NAICS
n/a
SIC 2221: Broadwoven Fabric Mills, Manmade Fiber and Silk
Sales Range $10
M
to 50
M
# of Employees 380
Plant Area
n/a
Annual Production 25,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $822,389 17,893,904
kWh
Natural Gas $189,524 42,746
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,625 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,790

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2122: Install / repair insulation on condensate lines $735 $775 - $735
-
MMBtu
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,681 $9,090 $8,681
188,746
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $16,835 $63,595 $16,835
366,354
kWh
-
04 2.4133: Use most efficient type of electric motors $7,813 $5,158 $7,813
169,988
kWh
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $3,561 $500 - $3,561
-
MMBtu
TOTAL RECOMMENDED $37,625 $79,118 $33,329
725,088
kWh
$4,296
-
MMBtu
TOTAL IMPLEMENTED $20,790 $15,523 $16,494
358,734
kWh
$4,296
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs