ITAC Assessment: GT0259
ITAC logo
ITAC Assessment: GT0259
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product MOLD INHIBITOR FOR FEED
NAICS
n/a
SIC 2879: Pesticides and Agricultural Chemicals, Not Elsewhere Classified
Sales Range less than $500
k
# of Employees 19
Plant Area
n/a
Annual Production 1,500,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,374 127,784
kWh
Natural Gas $7,102 1,164
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,070 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $80 $152 $80
879
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $230 $302 $230
2,345
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $300 $50 $300
2,931
kWh
-
04 2.2414: Use waste heat from hot flue gases to preheat $2,460 $6,830 - $2,460
-
MMBtu
TOTAL RECOMMENDED $3,070 $7,334 $610
6,155
kWh
$2,460
-
MMBtu
TOTAL IMPLEMENTED $610 $504 $610
6,155
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs