ITAC Assessment: GT0255
ITAC logo
ITAC Assessment: GT0255
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product HEAT PUMPS
NAICS
n/a
SIC 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area
n/a
Annual Production 8,200
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,177 390,094
kWh
Natural Gas $7,808 1,231
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,054 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,054

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $57 $57 $57
879
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,238 $1,459 $1,238
19,930
kWh
03 2.4321: Upgrade obsolete equipment $539 $400 $539
8,792
kWh
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,220 $400 $1,220
19,637
kWh
TOTAL RECOMMENDED $3,054 $2,316 $3,054
49,238
kWh
TOTAL IMPLEMENTED $3,054 $2,316 $3,054
49,238
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs