Assessment Year | 1984 |
---|---|
Principal Product | LOW DENSITY POLYETHYLENE |
NAICS |
n/a
|
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
n/a
|
Annual Production | 24,000,000
lb
|
Production Hrs. Annual | 8,484
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $319,920 | 8,546,893 |
kWh
|
$0.037 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,429 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7226: Use computer programs to optimize hvac performance | $23,586 | $16,000 |
$23,586
630,129
kWh
|
|
02 | 2.4133: Use most efficient type of electric motors | $1,843 | $1,729 |
$1,843
49,238
kWh
|
|
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $6,527 | $1,000 |
$6,527
174,385
kWh
|
|
04 | 2.2511: Insulate bare equipment | $1,657 | $190 |
$1,657
44,256
kWh
|
|
TOTAL RECOMMENDED | $33,613 | $18,919 |
$33,613
898,008
kWh
|
||
TOTAL IMPLEMENTED | $25,429 | $17,729 |
$25,429
679,367
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs