Assessment Year | 1984 |
---|---|
Principal Product | DYED & FINISHED PRODUCTS |
NAICS |
n/a
|
SIC | 2262: Finishers of Broadwoven Fabrics of Manmade Fiber and Silk |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 144,000
thousand feet
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $273,352 | 5,790,446 |
kWh
|
$0.047 |
Natural Gas | $797,195 | 191,447 |
MMBtu
|
$4.16 |
Fuel Oil #6 | $50,752 | 10,493 |
MMBtu
|
$4.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $297,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,717 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $20,387 | $200 | - |
$20,387
-
MMBtu
|
|
02 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $11,700 | $10,000 | - |
$11,700
-
MMBtu
|
|
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $188,200 | $270,000 | - |
$188,200
-
MMBtu
|
|
04 | 2.5192: Modify textile dryers | $51,600 | $23,000 | - |
$51,600
-
MMBtu
|
|
05 | 2.2135: Repair and eliminate steam leaks | $19,960 | $1,000 | - |
$19,960
-
MMBtu
|
|
06 | 2.2136: Install / repair insulation on steam lines | $1,670 | $640 | - |
$1,670
-
MMBtu
|
|
07 | 2.2122: Install / repair insulation on condensate lines | $1,040 | $400 | - |
$1,040
-
MMBtu
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,890 | $2,520 |
$2,890
61,547
kWh
|
- | |
TOTAL RECOMMENDED | $297,447 | $307,760 |
$2,890
61,547
kWh
|
$294,557
-
MMBtu
|
||
TOTAL IMPLEMENTED | $53,717 | $11,840 | - |
$53,717
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs