| Assessment Year | 1984 |
|---|---|
| Principal Product | DYED & FINISHED PRODUCTS |
| NAICS |
n/a
|
| SIC | 2262: Finishers of Broadwoven Fabrics of Manmade Fiber and Silk |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 144,000
thousand feet
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $273,352 | 5,790,446 |
kWh
|
$0.047 |
| Natural Gas | $797,195 | 191,447 |
MMBtu
|
$4.16 |
| Fuel Oil #6 | $50,752 | 10,493 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $297,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,717 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $20,387 | $200 | - |
$20,387
-
MMBtu
|
|
| 02 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $11,700 | $10,000 | - |
$11,700
-
MMBtu
|
|
| 03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $188,200 | $270,000 | - |
$188,200
-
MMBtu
|
|
| 04 | 2.5192: Modify textile dryers | $51,600 | $23,000 | - |
$51,600
-
MMBtu
|
|
| 05 | 2.2135: Repair and eliminate steam leaks | $19,960 | $1,000 | - |
$19,960
-
MMBtu
|
|
| 06 | 2.2136: Install / repair insulation on steam lines | $1,670 | $640 | - |
$1,670
-
MMBtu
|
|
| 07 | 2.2122: Install / repair insulation on condensate lines | $1,040 | $400 | - |
$1,040
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,890 | $2,520 |
$2,890
61,547
kWh
|
- | |
| TOTAL RECOMMENDED | $297,447 | $307,760 |
$2,890
61,547
kWh
|
$294,557
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $53,717 | $11,840 | - |
$53,717
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs