Assessment Year | 1983 |
---|---|
Principal Product | 3FINISHED FABRIC |
NAICS |
n/a
|
SIC | 2261: Finishers of Broadwoven Fabrics of Cotton |
Sales Range | $10 M to 50M |
# of Employees | 154 |
Plant Area |
n/a
|
Annual Production | 45,000,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $288,695 | 5,448,124 |
kWh
|
$0.053 |
Natural Gas | $818,178 | 188,013 |
MMBtu
|
$4.35 |
Fuel Oil #6 | $15,295 | 3,192 |
MMBtu
|
$4.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $361,462 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $55,852 | $75,000 |
$(-11,766.0)
(-222,157)
kWh
|
$67,618
-
MMBtu
|
- | |
02 | 2.5192: Modify textile dryers | $28,720 | $50,000 | - |
$28,720
-
MMBtu
|
- | |
03 | 3.6123: Burn wood by-products for heat | $274,827 | $430,000 | - |
$302,827
-
MMBtu
|
$(-28,000.0) | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,063 | $1,850 |
$2,063
38,980
kWh
|
- | - | |
TOTAL RECOMMENDED | $361,462 | $556,850 |
$(-9,703.0)
(-183,177)
kWh
|
$399,165
-
MMBtu
|
$(-28,000.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs