Assessment Year | 1983 |
---|---|
Principal Product | BEARINGS |
NAICS |
n/a
|
SIC | 3562: Ball and Roller Bearings |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 4,800,000
lb
|
Production Hrs. Annual | 6,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $482,680 | 10,043,963 |
kWh
|
$0.048 |
Natural Gas | $109,736 | 20,880 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,548 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,997 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.7226: Use computer programs to optimize hvac performance | $20,601 | $6,500 |
$20,601
830,598
kWh
|
|
02 | 2.3191: Use demand controller or load shedder | $18,971 | $10,500 |
$18,971
-
kWh
|
|
03 | 2.4133: Use most efficient type of electric motors | $17,950 | $37,900 |
$17,950
373,388
kWh
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $9,026 | - |
$9,026
187,573
kWh
|
|
TOTAL RECOMMENDED | $66,548 | $54,900 |
$66,548
1,391,559
kWh
|
||
TOTAL IMPLEMENTED | $27,997 | $10,500 |
$27,997
187,573
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs