| Assessment Year | 1983 |
|---|---|
| Principal Product | TUFTED CARPET |
| NAICS |
n/a
|
| SIC | 2273: Carpets and Rugs |
| Sales Range | $100 M to 500M |
| # of Employees | 450 |
| Plant Area |
n/a
|
| Annual Production | 225,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $477,526 | 13,204,279 |
kWh
|
$0.036 |
| Natural Gas | $1,583,726 | 360,864 |
MMBtu
|
$4.39 |
| Fuel Oil #6 | $52,287 | 13,153 |
MMBtu
|
$3.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $449,340 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $48,100 | $500 | - |
$48,100
-
MMBtu
|
|
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $31,900 | $35,000 | - |
$31,900
-
MMBtu
|
|
| 03 | 2.2511: Insulate bare equipment | $2,450 | $800 | - |
$2,450
-
MMBtu
|
|
| 04 | 2.5191: Modify dye beck | $100,000 | - | - |
$100,000
-
MMBtu
|
|
| 05 | 2.5191: Modify dye beck | $190,000 | $213,000 | - |
$190,000
-
MMBtu
|
|
| 06 | 2.2444: Use hot process fluids to preheat incoming process fluids | $13,000 | $20,000 | - |
$13,000
-
MMBtu
|
|
| 07 | 2.5192: Modify textile dryers | $36,800 | $25,000 | - |
$36,800
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,890 | $14,342 |
$8,890
245,604
kWh
|
- | |
| 09 | 2.4133: Use most efficient type of electric motors | $18,200 | $89,800 |
$18,200
504,103
kWh
|
- | |
| TOTAL RECOMMENDED | $449,340 | $398,442 |
$27,090
749,707
kWh
|
$422,250
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs