ITAC Assessment: GT0163
ITAC logo
ITAC Assessment: GT0163
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product MILK & JUICES
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area
n/a
Annual Production 8,925
Tgal
Production Hrs. Annual 6,120
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,732 2,895,955
kWh
Natural Gas $85,845 19,573
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,753 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2135: Repair and eliminate steam leaks $11,800 $350 - $11,800
-
MMBtu
02 2.2437: Recover waste heat from equipment $6,087 $12,013 - $6,087
-
MMBtu
03 2.1233: Analyze flue gas for proper air/fuel ratio $4,946 $150 - $4,946
-
MMBtu
04 2.4133: Use most efficient type of electric motors $1,520 - $1,520
54,220
kWh
-
05 2.2514: Cover open tanks $1,400 $150 - $1,400
-
MMBtu
TOTAL RECOMMENDED $25,753 $12,663 $1,520
54,220
kWh
$24,233
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs