| Assessment Year | 2000 |
|---|---|
| Principal Product | Wheelchair Lifts and Hand Controls |
| NAICS |
n/a
|
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
36,800
ft2
|
| Annual Production | 12,550
pieces
|
| Production Hrs. Annual | 5,616
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $19,302 | 622,802 |
kWh
|
$0.031 |
| Electricity Demand | $16,396 | 2,160 |
kW-mo/yr
|
$7.59 |
| Electricity Fees | $5,208 | - |
|
- |
| LPG | $16,732 | 2,836 |
MMBtu
|
$5.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $640 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $447 | $44 |
$292
9,379
kWh
|
$155
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.3212: Optimize plant power factor | $301 | $560 | - | - | $301 | - | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,046 | $8,012 | - |
$774
-
kW-mo/yr
|
- |
$1,272
-
MMBtu
|
- | - | - | |
| 04 | 2.2442: Preheat combustion air with waste heat | $1,481 | $5,600 | - | - | - |
$1,481
-
MMBtu
|
- | - | - | |
| 05 | 3.5113: Sell oil to recycler | $412 | $320 | - | - | - | - |
$412
-
gal
|
- | - | |
| 06 | 4.441: Install automatic packing equipment | $1,033 | $4,000 | - | - | - | - | - | $1,033 | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $640 | $(-1,560.0) | - | - | - | - | - | - | $640 | |
| TOTAL RECOMMENDED | $6,360 | $16,976 |
$292
9,379
kWh
|
$929
-
kW-mo/yr
|
$301 |
$2,753
-
MMBtu
|
$412
-
gal
|
$1,033 | $640 | ||
| TOTAL IMPLEMENTED | $640 | $(-1,560.0) | - | - | - | - | - | - | $640 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs