Assessment Year | 2000 |
---|---|
Principal Product | Animal Feed |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 36 |
Plant Area |
20,000
ft2
|
Annual Production | 54,000
ton
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $61,429 | 1,472,743 |
kWh
|
$0.042 |
Electricity Demand | $37,851 | 6,396 |
kW-mo/yr
|
$5.92 |
Electricity Fees | $14,732 | - |
|
- |
Natural Gas | $17,951 | 6,112 |
MMBtu
|
$2.94 |
LPG | $2,114 | 309 |
MMBtu
|
$6.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $4,196 | $3,997 | n/a | - | - |
$4,196
-
MMBtu
|
- | - |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $762 | - | n/a | - | - |
$762
-
MMBtu
|
- | - |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,888 | $6,600 | n/a |
$2,114
50,117
kWh
|
$405
-
kW-mo/yr
|
$(-631.0)
-
MMBtu
|
- | - |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,182 | $1,702 | n/a |
$791
18,757
kWh
|
$391
-
kW-mo/yr
|
- | - | - |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $499 | $105 | n/a |
$499
8,499
kWh
|
- | - | - | - |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $252 | - | n/a | - | - | - |
$252
-
lb
|
- |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $420 | - | n/a | - | - | - | - | $420 |
TOTAL RECOMMENDED | $9,199 | $12,404 |
$3,404
77,373
kWh
|
$796
-
kW-mo/yr
|
$4,327
-
MMBtu
|
$252
-
lb
|
$420 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs