| Assessment Year | 2000 |
|---|---|
| Principal Product | Cheese and Whey Products |
| NAICS |
n/a
|
| SIC | 2022: Natural, Processed, and Imitation Cheese |
| Sales Range | $50 M to 100M |
| # of Employees | 100 |
| Plant Area |
121,500
ft2
|
| Annual Production | 73,600,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $424,178 | 17,199,297 |
kWh
|
$0.025 |
| Electricity Demand | $318,191 | 33,084 |
kW-mo/yr
|
$9.62 |
| Electricity Fees | $22,915 | - |
|
- |
| Natural Gas | $306,686 | 129,662 |
MMBtu
|
$2.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $170,565 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $159,914 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2515: Use optimum thickness insulation | $9,729 | $1,887 | - |
$9,729
-
MMBtu
|
- | |
| 02 | 2.2135: Repair and eliminate steam leaks | $7,418 | $1,190 | - |
$7,418
-
MMBtu
|
- | |
| 03 | 2.7135: Install occupancy sensors | $922 | $648 |
$922
36,928
kWh
|
- | - | |
| 04 | 4.611: Begin a practice of predictive / preventative maintenance | $400 | - | - | - | $400 | |
| 05 | 4.441: Install automatic packing equipment | $152,096 | $54,500 |
$(-212.0)
(-8,499)
kWh
|
- | $152,308 | |
| TOTAL RECOMMENDED | $170,565 | $58,225 |
$710
28,429
kWh
|
$17,147
-
MMBtu
|
$152,708 | ||
| TOTAL IMPLEMENTED | $159,914 | $55,690 |
$(-212.0)
(-8,499)
kWh
|
$7,418
-
MMBtu
|
$152,708 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs