ITAC Assessment: DS0157
ITAC logo
ITAC Assessment: DS0157
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Metal Finishing
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $5
M
to 10
M
# of Employees 110
Plant Area 42,000
ft2
Annual Production 39,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,253 1,685,522
kWh
Electricity Demand $51,407 6,876
kW-mo/yr
Electricity Fees $918 -
Natural Gas $96,092 21,376
MMBtu
LPG $2,817 281
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,099 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.2515: Use optimum thickness insulation $2,370 $688 $2,370
-
MMBtu
- -
02 3.4116: Meter recycled water (to reduce sewer charges) $5,432 $800 - $5,432
-
Tgal
-
03 4.821: Pay bills on time to avoid late fees $1,297 - - - $1,297
TOTAL RECOMMENDED $9,099 $1,488 $2,370
-
MMBtu
$5,432
-
Tgal
$1,297
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs