Assessment Year | 1999 |
---|---|
Principal Product | Aluminum Castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
92,036
ft2
|
Annual Production | 13,500,000
pieces
|
Production Hrs. Annual | 8,112
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,818 | 4,389,215 |
kWh
|
$0.030 |
Electricity Demand | $77,887 | 10,452 |
kW-mo/yr
|
$7.45 |
Electricity Fees | $6,406 | - |
|
- |
Natural Gas | $252,032 | 65,183 |
MMBtu
|
$3.87 |
LPG | $1,746 | 143 |
MMBtu
|
$12.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,446 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $76,996 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $6,312 | $2,897 |
$4,026
134,232
kWh
|
- |
$2,286
-
MMBtu
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $512 | $483 |
$512
16,999
kWh
|
- | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,552 | $15,640 |
$12,480
416,178
kWh
|
$8,940
-
kW-mo/yr
|
$(-6,868.0)
-
MMBtu
|
- | - | - | |
04 | 2.7314: Reduce ventilation air | $32,699 | $30,301 |
$4,501
150,059
kWh
|
- |
$28,198
-
MMBtu
|
- | - | - | |
05 | 3.1191: Change procedures / equipment / operating conditions | $29,468 | $37,220 | - | - |
$4,547
-
MMBtu
|
- | - | $24,921 | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $626 | $400 | - | - | - |
$626
-
Tgal
|
- | - | |
07 | 4.821: Pay bills on time to avoid late fees | $277 | - | - | - | - | - | $277 | - | |
TOTAL RECOMMENDED | $84,446 | $86,941 |
$21,519
717,468
kWh
|
$8,940
-
kW-mo/yr
|
$28,163
-
MMBtu
|
$626
-
Tgal
|
$277 | $24,921 | ||
TOTAL IMPLEMENTED | $76,996 | $83,161 |
$16,981
566,237
kWh
|
$8,940
-
kW-mo/yr
|
$25,877
-
MMBtu
|
- | $277 | $24,921 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs