| Assessment Year | 1999 |
|---|---|
| Principal Product | Security Doors and Frames |
| NAICS |
n/a
|
| SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
| Sales Range | $10 M to 50M |
| # of Employees | 171 |
| Plant Area |
100,000
ft2
|
| Annual Production | 65,000
pieces
|
| Production Hrs. Annual | 5,564
hrs
|
| Location (State) | South Dakota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $62,281 | 2,197,538 |
kWh
|
$0.028 |
| Electricity Demand | $43,926 | 5,616 |
kW-mo/yr
|
$7.82 |
| Electricity Fees | $6,011 | - |
|
- |
| Natural Gas | $28,434 | 8,614 |
MMBtu
|
$3.30 |
| LPG | $3,133 | 275 |
MMBtu
|
$11.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,641 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,540 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $835 | $2,974 |
$422
14,947
kWh
|
$413
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,395 | $351 |
$2,743
97,890
kWh
|
$1,652
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $5,760 | $6,500 | - | - |
$5,760
-
MMBtu
|
- | - | - | - | |
| 04 | 2.2511: Insulate bare equipment | $11,263 | $22,640 | - | - |
$11,263
-
MMBtu
|
- | - | - | - | |
| 05 | 3.4111: Use closed cycle process to minimize waste water production | $6,203 | $15,000 |
$(-974.0)
(-34,877)
kWh
|
$(-1,389.0)
-
kW-mo/yr
|
- |
$4,283
-
Tgal
|
- | - |
$4,283
-
Tgal
|
|
| 06 | 4.515: Install shelves / racks to utilize unused space | $3,290 | $12,726 | - | - | - | - | - | $3,290 | - | |
| 07 | 3.2176: Increase use of automation | $3,744 | $160 | - | - | - | - | $3,744 | - | - | |
| 08 | 4.211: Consider use / purchase of bulk materials where possible | $1,875 | $3,856 | - | - | - | - | - | $1,875 | - | |
| 09 | 4.211: Consider use / purchase of bulk materials where possible | $14,276 | $9,589 | - | - | - | - | - | $14,276 | - | |
| TOTAL RECOMMENDED | $51,641 | $73,796 |
$2,191
77,960
kWh
|
$676
-
kW-mo/yr
|
$17,023
-
MMBtu
|
$4,283
-
Tgal
|
$3,744 | $19,441 |
$4,283
-
Tgal
|
||
| TOTAL IMPLEMENTED | $26,540 | $25,800 |
$3,165
112,837
kWh
|
$2,065
-
kW-mo/yr
|
- | - | $3,744 | $17,566 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs