Assessment Year | 1998 |
---|---|
Principal Product | Canned and Frozen Peas and Corn |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $50 M to 100M |
# of Employees | 1,400 |
Plant Area |
467,083
ft2
|
Annual Production | 146,466,247
lb
|
Production Hrs. Annual | 2,304
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $825,927 | 20,642,732 |
kWh
|
$0.040 |
Electricity Demand | $264,685 | 41,040 |
kW-mo/yr
|
$6.45 |
Electricity Fees | $42,608 | - |
|
- |
Natural Gas | $309,918 | 111,876 |
MMBtu
|
$2.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,934 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,385 | $21,938 |
$3,464
101,993
kWh
|
$921
-
kW-mo/yr
|
- | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,039 | $2,213 | - |
$2,039
-
kW-mo/yr
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $30,549 | $25,900 | - | - | $30,549 | - | - | |
04 | 2.2511: Insulate bare equipment | $15,838 | $30,000 | - | - | - |
$15,838
-
MMBtu
|
- | |
05 | 3.2176: Increase use of automation | $6,750 | $10,000 | - | - | - | - | $6,750 | |
06 | 3.2176: Increase use of automation | $15,206 | $40,000 |
$8,456
120,750
kWh
|
- | - | - | $6,750 | |
TOTAL RECOMMENDED | $74,767 | $130,051 |
$11,920
222,743
kWh
|
$2,960
-
kW-mo/yr
|
$30,549 |
$15,838
-
MMBtu
|
$13,500 | ||
TOTAL IMPLEMENTED | $34,934 | $47,838 |
$3,464
101,993
kWh
|
$921
-
kW-mo/yr
|
$30,549 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs