| Assessment Year | 1998 |
|---|---|
| Principal Product | Wire Fixtures and Displays |
| NAICS |
n/a
|
| SIC | 3490: |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
140,000
ft2
|
| Annual Production | 1,200,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,155 | 1,995,897 |
kWh
|
$0.036 |
| Electricity Demand | $37,715 | 4,980 |
kW-mo/yr
|
$7.57 |
| Electricity Fees | $(-1,647.0) | - |
|
- |
| Natural Gas | $55,682 | 12,378 |
MMBtu
|
$4.50 |
| LPG | $11,050 | 957 |
MMBtu
|
$11.55 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $19,667 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,333 | $13,988 |
$3,787
105,217
kWh
|
$1,546
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 3.5316: Contract a wood pallet recycling company | $1,630 | $160 | - | - | - | - | $1,630 | - | |
| 03 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,579 | $4,750 | - | - |
$4,195
-
lb
|
$(-104.0) | $488 | - | |
| 04 | 3.2176: Increase use of automation | $2,600 | $4,900 | - | - | - | $2,600 | - | - | |
| 05 | 4.211: Consider use / purchase of bulk materials where possible | $5,525 | $1,350 | - | - | - | - | - | $5,525 | |
| TOTAL RECOMMENDED | $19,667 | $25,148 |
$3,787
105,217
kWh
|
$1,546
-
kW-mo/yr
|
$4,195
-
lb
|
$2,496 | $2,118 | $5,525 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs