ITAC Assessment: DS0111
ITAC logo
ITAC Assessment: DS0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Thermal injection moldings
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 92,000
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $193,687 4,646,835
kWh
Electricity Demand $24,353 11,666
kW-mo/yr
Electricity Fees $3,543 -
Natural Gas $23,561 4,133
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,456 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,604

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,394 $7,486 $5,910
140,680
kWh
$484
-
kW-mo/yr
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $11,145 - - $11,145
-
kW-mo/yr
- - -
03 2.1335: Replace gasoline with diesel, lpg, or natural gas $10,786 $30,000 - - - - $10,786
04 3.5315: Lease / purchase baler; sell cardboard to recycler $9,066 $4,500 - - - $9,066
-
lb
-
05 3.4116: Meter recycled water (to reduce sewer charges) $3,065 $1,600 - - $3,065
-
Tgal
- -
TOTAL RECOMMENDED $40,456 $43,586 $5,910
140,680
kWh
$11,629
-
kW-mo/yr
$3,065
-
Tgal
$9,066
-
lb
$10,786
TOTAL IMPLEMENTED $20,604 $9,086 $5,910
140,680
kWh
$11,629
-
kW-mo/yr
$3,065
-
Tgal
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs