ITAC Assessment: DS0106
ITAC logo
ITAC Assessment: DS0106
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Waterbase and Hot Melt Adhesives
NAICS
n/a
SIC 2891: Adhesives and Sealants
Sales Range $10
M
to 50
M
# of Employees 43
Plant Area 54,259
ft2
Annual Production 21,600,000
lb
Production Hrs. Annual 7,150
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,953 1,897,128
kWh
Electricity Demand $33,165 4,368
kW-mo/yr
Electricity Fees $10,361 -
Natural Gas $73,600 18,451
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,131 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings
01 2.2511: Insulate bare equipment $3,231 $2,430 $3,231
-
MMBtu
- - - - -
02 2.2135: Repair and eliminate steam leaks $1,009 $400 $877
-
MMBtu
$104
-
Tgal
- - - $28
-
Tgal
03 3.1191: Change procedures / equipment / operating conditions $15,659 $199 - $8,545
-
Tgal
- - $7,114 -
04 3.5316: Contract a wood pallet recycling company $4,680 $160 - - - $4,680 - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $3,552 $4,750 - - $3,552
-
lb
- - -
TOTAL RECOMMENDED $28,131 $7,939 $4,108
-
MMBtu
$8,649
-
Tgal
$3,552
-
lb
$4,680 $7,114 $28
-
Tgal
TOTAL IMPLEMENTED $12,472 $7,740 $4,108
-
MMBtu
$104
-
Tgal
$3,552
-
lb
$4,680 - $28
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs