| Assessment Year | 1998 |
|---|---|
| Principal Product | Window and Door Hardware |
| NAICS |
n/a
|
| SIC | 3429: Hardware, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 495 |
| Plant Area |
200,000
ft2
|
| Annual Production | 132,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $274,377 | 10,639,215 |
kWh
|
$0.026 |
| Electricity Demand | $217,549 | 18,348 |
kW-mo/yr
|
$11.86 |
| Electricity Fees | $22,273 | - |
|
- |
| Natural Gas | $126,935 | 58,427 |
MMBtu
|
$2.17 |
| LPG | $34,389 | 2,547 |
MMBtu
|
$13.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,618 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,259 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,845 | $12,803 |
$3,112
119,871
kWh
|
$2,733
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $488 | $156 |
$260
9,965
kWh
|
$228
-
kW-mo/yr
|
- | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $2,584 | $822 |
$1,759
67,702
kWh
|
$825
-
kW-mo/yr
|
- | - | |
| 04 | 3.5316: Contract a wood pallet recycling company | $15,180 | $160 | - | - |
$15,180
-
lb
|
- | |
| 05 | 3.7214: Reduce or eliminate waste | $5,771 | $1,510 | - | - |
$5,771
-
lb
|
- | |
| 06 | 3.1175: Use a different or recycled raw material | $3,750 | $160 | - | - | - | $3,750 | |
| TOTAL RECOMMENDED | $33,618 | $15,611 |
$5,131
197,538
kWh
|
$3,786
-
kW-mo/yr
|
$20,951
-
lb
|
$3,750 | ||
| TOTAL IMPLEMENTED | $6,259 | $1,666 |
$260
9,965
kWh
|
$228
-
kW-mo/yr
|
$5,771
-
lb
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs