ITAC Assessment: DS0104
ITAC logo
ITAC Assessment: DS0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Window and Door Hardware
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 495
Plant Area 200,000
ft2
Annual Production 132,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,377 10,639,215
kWh
Electricity Demand $217,549 18,348
kW-mo/yr
Electricity Fees $22,273 -
Natural Gas $126,935 58,427
MMBtu
LPG $34,389 2,547
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,618 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,259

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,845 $12,803 $3,112
119,871
kWh
$2,733
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $488 $156 $260
9,965
kWh
$228
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $2,584 $822 $1,759
67,702
kWh
$825
-
kW-mo/yr
- -
04 3.5316: Contract a wood pallet recycling company $15,180 $160 - - $15,180
-
lb
-
05 3.7214: Reduce or eliminate waste $5,771 $1,510 - - $5,771
-
lb
-
06 3.1175: Use a different or recycled raw material $3,750 $160 - - - $3,750
TOTAL RECOMMENDED $33,618 $15,611 $5,131
197,538
kWh
$3,786
-
kW-mo/yr
$20,951
-
lb
$3,750
TOTAL IMPLEMENTED $6,259 $1,666 $260
9,965
kWh
$228
-
kW-mo/yr
$5,771
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs