ITAC Assessment: DS0096
ITAC logo
ITAC Assessment: DS0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Magazines
NAICS
n/a
SIC 2579:
Sales Range $50
M
to 100
M
# of Employees 543
Plant Area 310,000
ft2
Annual Production 100,000,000
pieces
Production Hrs. Annual 8,344
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $555,379 17,719,227
kWh
Electricity Demand $248,009 39,408
kW-mo/yr
Electricity Fees $2,610 -
Natural Gas $130,685 48,618
MMBtu
LPG $28,562 5,738
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $124,045 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $84,930

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.2437: Recover waste heat from equipment $14,674 $50,000 - - $14,674
-
MMBtu
- - - -
02 2.4239: Eliminate or reduce compressed air usage $23,816 $30,000 $16,811
542,497
kWh
$7,005
-
kW-mo/yr
- - - - -
03 3.5316: Contract a wood pallet recycling company $625 $100 - - - - - $625 -
04 3.5311: Recover and reuse waste material $3,938 $500 - - - $2,700
-
gal
- - $1,238
05 3.2176: Increase use of automation $80,992 $100,000 - - - - $80,992 - -
TOTAL RECOMMENDED $124,045 $180,600 $16,811
542,497
kWh
$7,005
-
kW-mo/yr
$14,674
-
MMBtu
$2,700
-
gal
$80,992 $625 $1,238
TOTAL IMPLEMENTED $84,930 $100,500 - - - $2,700
-
gal
$80,992 - $1,238
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs