| Assessment Year | 1997 |
|---|---|
| Principal Product | Magazines |
| NAICS |
n/a
|
| SIC | 2579: |
| Sales Range | $50 M to 100M |
| # of Employees | 543 |
| Plant Area |
310,000
ft2
|
| Annual Production | 100,000,000
pieces
|
| Production Hrs. Annual | 8,344
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $555,379 | 17,719,227 |
kWh
|
$0.031 |
| Electricity Demand | $248,009 | 39,408 |
kW-mo/yr
|
$6.29 |
| Electricity Fees | $2,610 | - |
|
- |
| Natural Gas | $130,685 | 48,618 |
MMBtu
|
$2.69 |
| LPG | $28,562 | 5,738 |
MMBtu
|
$4.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $124,045 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $84,930 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $14,674 | $50,000 | - | - |
$14,674
-
MMBtu
|
- | - | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $23,816 | $30,000 |
$16,811
542,497
kWh
|
$7,005
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 3.5316: Contract a wood pallet recycling company | $625 | $100 | - | - | - | - | - | $625 | - | |
| 04 | 3.5311: Recover and reuse waste material | $3,938 | $500 | - | - | - |
$2,700
-
gal
|
- | - | $1,238 | |
| 05 | 3.2176: Increase use of automation | $80,992 | $100,000 | - | - | - | - | $80,992 | - | - | |
| TOTAL RECOMMENDED | $124,045 | $180,600 |
$16,811
542,497
kWh
|
$7,005
-
kW-mo/yr
|
$14,674
-
MMBtu
|
$2,700
-
gal
|
$80,992 | $625 | $1,238 | ||
| TOTAL IMPLEMENTED | $84,930 | $100,500 | - | - | - |
$2,700
-
gal
|
$80,992 | - | $1,238 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs