ITAC Assessment: DS0079
ITAC logo
ITAC Assessment: DS0079
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Aircraft Test Equipment
NAICS
n/a
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 40,740
ft2
Annual Production 16
pieces
Production Hrs. Annual 3,380
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,656 621,336
kWh
Electricity Demand $16,843 2,436
kW-mo/yr
Electricity Fees $1,488 -
Natural Gas $12,362 2,685
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,841 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,893

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,837 $15,866 $2,280
63,306
kWh
$1,557
-
kW-mo/yr
- - - - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $161 $260 $161
4,396
kWh
- - - - - - -
03 3.8142: Distill contaminated solvents for reuse $1,071 $6,000 - - $(-89.0)
-
Tgal
$820
-
gal
- - $483 $(-143.0)
-
Tgal
04 3.5315: Lease / purchase baler; sell cardboard to recycler $1,040 $4,750 - - - - $1,040
-
lb
- - -
05 3.2124: Convert to air assisted / airless paint guns $5,732 $7,500 - - - $2,080
-
gal
- $3,652 - -
TOTAL RECOMMENDED $11,841 $34,376 $2,441
67,702
kWh
$1,557
-
kW-mo/yr
$(-89.0)
-
Tgal
$2,900
-
gal
$1,040
-
lb
$3,652 $483 $(-143.0)
-
Tgal
TOTAL IMPLEMENTED $5,893 $7,760 $161
4,396
kWh
- - $2,080
-
gal
- $3,652 - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs