ITAC Assessment: DS0077
ITAC logo
ITAC Assessment: DS0077
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Food Containers
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 27
Plant Area 12,160
ft2
Annual Production 1,467,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,086 937,280
kWh
Electricity Demand $20,358 3,624
kW-mo/yr
Electricity Fees $54 -
LPG $6,038 798
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,807 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,456

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,294 $3,482 $883
33,998
kWh
$411
-
kW-mo/yr
- -
02 2.6212: Turn off equipment during breaks, reduce operating time $162 $24 $162
6,155
kWh
- - -
03 3.4116: Meter recycled water (to reduce sewer charges) $1,078 $750 - - $1,078
-
Tgal
-
04 3.2176: Increase use of automation $47,273 $6,500 $(-232.0)
(-8,792)
kWh
$(-95.0)
-
kW-mo/yr
- $47,600
TOTAL RECOMMENDED $49,807 $10,756 $813
31,361
kWh
$316
-
kW-mo/yr
$1,078
-
Tgal
$47,600
TOTAL IMPLEMENTED $1,456 $3,506 $1,045
40,153
kWh
$411
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs