ITAC Assessment: DS0069
ITAC logo
ITAC Assessment: DS0069
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Grain Augers and Service Truck Bodies
NAICS
n/a
SIC 3514:
Sales Range $10
M
to 50
M
# of Employees 124
Plant Area 33,980
ft2
Annual Production 15,500
pieces
Production Hrs. Annual 2,860
hrs
Location (State) South Dakota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,678 859,027
kWh
Electricity Demand $29,590 3,912
kW-mo/yr
Electricity Fees $3,713 -
Natural Gas $24,236 5,050
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,829 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,223

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,691 $4,761 $811
26,084
kWh
$880
-
kW-mo/yr
- -
02 2.6218: Turn off equipment when not in use $969 - $434
14,068
kWh
$535
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $206 $3,216 $84
2,638
kWh
$122
-
kW-mo/yr
- -
04 4.431: Train operators for maximum operating efficiency $6,240 $100 - - $6,240 -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,323 $600 $1,323
42,790
kWh
- - -
06 4.431: Train operators for maximum operating efficiency $8,400 $6,720 - - - $8,400
TOTAL RECOMMENDED $18,829 $15,397 $2,652
85,580
kWh
$1,537
-
kW-mo/yr
$6,240 $8,400
TOTAL IMPLEMENTED $10,223 $5,461 $2,568
82,942
kWh
$1,415
-
kW-mo/yr
$6,240 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs