Assessment Year | 1996 |
---|---|
Principal Product | Doors & Cabinets |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 37 |
Plant Area |
63,000
ft2
|
Annual Production | 8,300
pieces
|
Production Hrs. Annual | 2,795
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $28,327 | 912,075 |
kWh
|
$0.031 |
Electricity Demand | $25,666 | 3,408 |
kW-mo/yr
|
$7.53 |
Electricity Fees | $8,653 | - |
|
- |
Natural Gas | $26,958 | 5,431 |
MMBtu
|
$4.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,626 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $22,626 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $993 | $2,300 |
$319
10,258
kWh
|
$674
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $854 | $200 |
$565
18,171
kWh
|
$289
-
kW-mo/yr
|
- | - | - | |
03 | 2.3212: Optimize plant power factor | $2,466 | $1,050 | - | - | - | - | $2,466 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,120 | $11,350 |
$2,674
85,873
kWh
|
$1,446
-
kW-mo/yr
|
- | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $4,951 | $4,500 | - | - | - |
$4,951
-
lb
|
- | |
06 | 2.7224: Reduce space conditioning during non-working hours | $9,242 | $2,400 | - | - |
$9,242
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $22,626 | $21,800 |
$3,558
114,302
kWh
|
$2,409
-
kW-mo/yr
|
$9,242
-
MMBtu
|
$4,951
-
lb
|
$2,466 | ||
TOTAL IMPLEMENTED | $22,626 | $21,800 |
$3,558
114,302
kWh
|
$2,409
-
kW-mo/yr
|
$9,242
-
MMBtu
|
$4,951
-
lb
|
$2,466 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs