ITAC Assessment: DS0053
ITAC logo
ITAC Assessment: DS0053
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Malt
NAICS
n/a
SIC 2083: Malt
Sales Range $10
M
to 50
M
# of Employees 51
Plant Area 358,000
ft2
Annual Production 6,529,000
bushels
Production Hrs. Annual 8,760
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $358,101 19,269,344
kWh
Electricity Demand $417,209 45,084
kW-mo/yr
Electricity Fees $5,215 -
Natural Gas $335,303 192,017
MMBtu
Fuel Oil #2 $1,388 230
MMBtu
Fuel Oil #6 $547,067 346,356
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $177,955 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $177,955

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #6 Savings Water Disposal Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,015 $17,930 $2,550
150,059
kWh
$2,465
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $10,065 $48,791 $3,807
223,916
kWh
$6,258
-
kW-mo/yr
- - -
03 3.4151: Minimize water usage $113,670 $1,000 - - - - $113,670
-
Tgal
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,379 $48,780 $12,960
762,603
kWh
$3,419
-
kW-mo/yr
- - -
05 2.2121: Increase amount of condensate returned $32,826 $17,550 - - $4,665
-
MMBtu
$7,369
-
MMBtu
$20,792
-
Tgal
TOTAL RECOMMENDED $177,955 $134,051 $19,317
1,136,578
kWh
$12,142
-
kW-mo/yr
$4,665
-
MMBtu
$7,369
-
MMBtu
$134,462
-
Tgal
TOTAL IMPLEMENTED $177,955 $134,051 $19,317
1,136,578
kWh
$12,142
-
kW-mo/yr
$4,665
-
MMBtu
$7,369
-
MMBtu
$134,462
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs