Assessment Year | 1996 |
---|---|
Principal Product | Metal Fabrication |
NAICS |
n/a
|
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
51,025
ft2
|
Annual Production | 6,068,938
lb
|
Production Hrs. Annual | 6,660
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $79,451 | 2,219,812 |
kWh
|
$0.036 |
Electricity Demand | $28,162 | 7,716 |
kW-mo/yr
|
$3.65 |
Electricity Fees | $1,329 | - |
|
- |
Natural Gas | $42,439 | 4,154 |
MMBtu
|
$10.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,006 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $94,006 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,357 | $8,346 |
$1,809
50,410
kWh
|
$548
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $1,931 | $1,299 |
$1,475
39,859
kWh
|
$456
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,213 | $220 |
$5,213
144,783
kWh
|
- | - | - | |
04 | 2.6218: Turn off equipment when not in use | $895 | - |
$895
24,912
kWh
|
- | - | - | |
05 | 3.2121: Convert to electrostatic powder coating | $19,183 | $4,200 | - | - |
$19,057
-
gal
|
$126
-
lb
|
|
06 | 3.2121: Convert to electrostatic powder coating | $64,427 | $6,000 | - | - |
$64,364
-
gal
|
$63
-
lb
|
|
TOTAL RECOMMENDED | $94,006 | $20,065 |
$9,392
259,964
kWh
|
$1,004
-
kW-mo/yr
|
$83,421
-
gal
|
$189
-
lb
|
||
TOTAL IMPLEMENTED | $94,006 | $20,065 |
$9,392
259,964
kWh
|
$1,004
-
kW-mo/yr
|
$83,421
-
gal
|
$189
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs