ITAC Assessment: DS0047
ITAC logo
ITAC Assessment: DS0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Steel Storage Tanks
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $1
M
to 5
M
# of Employees 15
Plant Area 28,227
ft2
Annual Production 900
pieces
Production Hrs. Annual 2,600
hrs
Location (State) North Dakota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $8,767 263,482
kWh
Electricity Demand $15,752 1,992
kW-mo/yr
Electricity Fees $490 -
Natural Gas $14,310 3,434
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,952 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,202

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $2,167 $2,391 - $2,167
-
kW-mo/yr
- -
02 2.4322: Use or replace with energy efficient substitutes $1,884 $5,600 $542
15,533
kWh
$1,342
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $595 $2,186 $90
2,638
kWh
$505
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $461 $50 $461
13,189
kWh
- - -
05 3.2121: Convert to electrostatic powder coating $7,750 $10,200 - - - $7,750
06 2.7232: Replace existing hvac unit with high efficiency model $3,602 $11,180 - - $3,602
-
MMBtu
-
07 2.7447: Install vinyl strip / high speed / air curtain doors $2,493 $1,975 - - $2,493
-
MMBtu
-
TOTAL RECOMMENDED $18,952 $33,582 $1,093
31,360
kWh
$4,014
-
kW-mo/yr
$6,095
-
MMBtu
$7,750
TOTAL IMPLEMENTED $11,202 $23,382 $1,093
31,360
kWh
$4,014
-
kW-mo/yr
$6,095
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs