Assessment Year | 1996 |
---|---|
Principal Product | Steel Storage Tanks |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
28,227
ft2
|
Annual Production | 900
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | North Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $8,767 | 263,482 |
kWh
|
$0.033 |
Electricity Demand | $15,752 | 1,992 |
kW-mo/yr
|
$7.91 |
Electricity Fees | $490 | - |
|
- |
Natural Gas | $14,310 | 3,434 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,202 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $2,167 | $2,391 | - |
$2,167
-
kW-mo/yr
|
- | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $1,884 | $5,600 |
$542
15,533
kWh
|
$1,342
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $595 | $2,186 |
$90
2,638
kWh
|
$505
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $461 | $50 |
$461
13,189
kWh
|
- | - | - | |
05 | 3.2121: Convert to electrostatic powder coating | $7,750 | $10,200 | - | - | - | $7,750 | |
06 | 2.7232: Replace existing hvac unit with high efficiency model | $3,602 | $11,180 | - | - |
$3,602
-
MMBtu
|
- | |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,493 | $1,975 | - | - |
$2,493
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $18,952 | $33,582 |
$1,093
31,360
kWh
|
$4,014
-
kW-mo/yr
|
$6,095
-
MMBtu
|
$7,750 | ||
TOTAL IMPLEMENTED | $11,202 | $23,382 |
$1,093
31,360
kWh
|
$4,014
-
kW-mo/yr
|
$6,095
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs