ITAC Assessment: DS0028
ITAC logo
ITAC Assessment: DS0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Fresh and Frozen Turkey
NAICS
n/a
SIC 2135:
Sales Range $100
M
to 500
M
# of Employees 480
Plant Area 153,364
ft2
Annual Production 200,000,000
lb
Production Hrs. Annual 4,896
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $510,140 15,436,401
kWh
Natural Gas $114,377 44,092
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,822 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,646

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,193 $4,683 $2,193
70,633
kWh
-
02 2.7135: Install occupancy sensors $496 $900 $496
33,118
kWh
-
03 2.4133: Use most efficient type of electric motors $8,625 $25,658 $8,625
215,123
kWh
-
04 2.2422: Use waste heat from hot flue gases to generate steam $153 $300 - $153
-
MMBtu
05 2.2511: Insulate bare equipment $310 $485 $310
20,809
kWh
-
06 2.2511: Insulate bare equipment $365 $78 - $365
-
MMBtu
07 2.3113: Make ice during off peak hours for cooling $50,680 $81,020 $50,680
-
kWh
-
TOTAL RECOMMENDED $62,822 $113,124 $62,304
339,683
kWh
$518
-
MMBtu
TOTAL IMPLEMENTED $11,646 $31,204 $11,128
306,565
kWh
$518
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs