| Assessment Year | 1995 |
|---|---|
| Principal Product | Packaged Beef, Packaged Pork |
| NAICS |
n/a
|
| SIC | 2021: Creamery Butter |
| Sales Range | $10 M to 50M |
| # of Employees | 142 |
| Plant Area |
82,755
ft2
|
| Annual Production | 26,000,000
lb
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $199,889 | 4,513,482 |
kWh
|
$0.044 |
| Natural Gas | $35,126 | 7,377 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,648 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,015 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,015 | $1,423 |
$1,015
22,274
kWh
|
- | |
| 02 | 2.7135: Install occupancy sensors | $2,292 | $5,958 |
$2,292
73,857
kWh
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $5,509 | $7,430 |
$5,509
112,837
kWh
|
- | |
| 04 | 2.3212: Optimize plant power factor | $4,989 | $16,420 |
$4,989
-
kWh
|
- | |
| 05 | 2.2511: Insulate bare equipment | $905 | $177 | - |
$905
-
MMBtu
|
|
| 06 | 2.2511: Insulate bare equipment | $595 | $77 | - |
$595
-
MMBtu
|
|
| 07 | 2.2511: Insulate bare equipment | $158 | $87 |
$158
5,275
kWh
|
- | |
| 08 | 2.2437: Recover waste heat from equipment | $10,397 | $15,000 | - |
$10,397
-
MMBtu
|
|
| 09 | 2.6218: Turn off equipment when not in use | $2,990 | - |
$2,990
96,424
kWh
|
- | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $798 | $599 |
$798
25,791
kWh
|
- | |
| TOTAL RECOMMENDED | $29,648 | $47,171 |
$17,751
336,458
kWh
|
$11,897
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,015 | $1,423 |
$1,015
22,274
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs