| Assessment Year | 2026 |
|---|---|
| Principal Product | Asphalt |
| NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $10 M to 50M |
| # of Employees | 85 |
| Plant Area |
15,988,855
ft2
|
| Annual Production | 492,537
ton
|
| Production Hrs. Annual | 2,400
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,066,832 | 7,642,237 |
kWh
|
$0.14 |
| Electricity Demand | $203,243 | 44,254 |
kW-mo/yr
|
$4.59 |
| Electricity Fees | $24,456 | - |
|
- |
| Natural Gas | $724,926 | 141,902 |
MMBtu
|
$5.11 |
| Other Gas | $31,438 | 1 |
MMBtu
|
$31,438.00 |
| TOTAL YEARLY COSTS | $2,050,895 | |||
| RECOMMENDED SAVINGS* | $196,951 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $54,924 | $200,000 |
$54,924
330,866
kWh
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,040 | $12,900 |
$3,040
18,312
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,725 | $23,500 |
$5,725
34,488
kWh
|
- | |
| 04 | 2.1221: Replace obsolete burners with more efficient ones | $34,850 | $150,000 | - |
$34,850
-
MMBtu
|
|
| 05 | 2.4313: Provide proper maintenance of motor driven equipment | $48,372 | $50,000 |
$48,372
291,396
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $50,040 | $42,000 |
$50,040
301,445
kWh
|
- | |
| TOTAL RECOMMENDED | $196,951 | $478,400 |
$162,101
976,507
kWh
|
$34,850
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs