Assessment Year | 2023 |
---|---|
Principal Product | life sciences instrumentation |
NAICS | 334516: Analytical Laboratory Instrument Manufacturing |
SIC | 3826: Laboratory Analytical Instruments |
Sales Range | $50 M to 100M |
# of Employees | 490 |
Plant Area |
354,000
ft2
|
Annual Production | 200
units
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $266,934 | 3,114,056 |
kWh
|
$0.086 |
Electricity Demand | $70,870 | 15,085 |
kW-mo/yr
|
$4.70 |
Electricity Fees | $8,294 | - |
|
- |
Natural Gas | $429,996 | 72,317 |
MMBtu
|
$5.95 |
TOTAL YEARLY COSTS | $776,094 | |||
RECOMMENDED SAVINGS* | $254,792 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,353 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $61,397 | - |
$61,397
568,493
kWh
|
- | |
02 | 2.7314: Reduce ventilation air | $32,353 | - |
$18,693
173,080
kWh
|
$13,660
-
MMBtu
|
|
03 | 2.2211: Use optimum temperature | $8,303 | - |
$17,012
157,517
kWh
|
$(-8,709.0)
-
MMBtu
|
|
04 | 2.7132: Install timers on light switches in little used areas | $44,923 | $1,275 |
$44,923
415,956
kWh
|
- | |
05 | 2.7234: Use heat pump for space conditioning | $2,948 | $14,000 |
$1,341
12,420
kWh
|
$1,607
-
MMBtu
|
|
06 | 2.7232: Replace existing hvac unit with high efficiency model | $104,868 | $500,000 |
$77,496
717,554
kWh
|
$27,372
-
MMBtu
|
|
TOTAL RECOMMENDED | $254,792 | $515,275 |
$220,862
2,045,020
kWh
|
$33,930
-
MMBtu
|
||
TOTAL IMPLEMENTED | $32,353 | - |
$18,693
173,080
kWh
|
$13,660
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs