Assessment Year | 2023 |
---|---|
Principal Product | Aluminum wire |
NAICS | 331318: Other Aluminum Rolling, Drawing, and Extruding |
SIC | 3355: Aluminum Rolling and Drawing, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
55,000
ft2
|
Annual Production | 2,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $416,795 | 5,167,968 |
kWh
|
$0.081 | |
Natural Gas | $18,136 | 1,238 |
MMBtu
|
$14.65 | |
Waste Disposal Costs | |||||
Water Usage | $124,732 | 12,072 |
Tgal
|
$10.33 | |
TOTAL YEARLY COSTS | $559,663 | ||||
RECOMMENDED SAVINGS* | $93,726 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $49,619 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 2.4235: Remove or close off unneeded compressed air lines | $6,327 | - |
$6,327
78,105
kWh
|
- | - | |
02 | 2.4235: Remove or close off unneeded compressed air lines | $6,327 | - |
$6,327
78,105
kWh
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,072 | $500 |
$2,072
25,585
kWh
|
- | - | |
04 | 2.4237: Substitute compressed air cooling with water or air cooling | $15,801 | $4,102 |
$15,801
195,078
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,896 | - |
$5,896
72,788
kWh
|
- | - | |
06 | 2.2511: Insulate bare equipment | $4,181 | $6,480 |
$4,181
51,615
kWh
|
- | - | |
07 | 3.7121: Improve handling practices | $25,825 | $10,000 | - | - |
$25,825
-
Tgal
|
|
08 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $9,068 | $28,750 | - |
$9,068
-
MMBtu
|
- | |
09 | 2.2314: Replace heat treating oven with more efficient unit | $18,229 | $60,000 |
$18,229
225,051
kWh
|
- | - | |
TOTAL RECOMMENDED | $93,726 | $109,832 |
$58,833
726,327
kWh
|
$9,068
-
MMBtu
|
$25,825
-
Tgal
|
||
TOTAL IMPLEMENTED | $49,619 | $39,250 |
$14,726
181,795
kWh
|
$9,068
-
MMBtu
|
$25,825
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs