ITAC Assessment: DL0213
ITAC logo
ITAC Assessment: DL0213
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product PVC films and Laminates
NAICS 325211: Plastics Material and Resin Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 140,177
ft2
Annual Production 15,541,265
lb
Production Hrs. Annual 8,424
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $514,602 11,948,341
kWh
Electricity Demand $238,667 22,962
kW-mo/yr
Electricity Fees $112,320 -
Natural Gas $1,296,523 141,239
MMBtu
Waste Disposal Costs
Water Usage $31,274 15,089
Tgal
Water Disposal $77,725 15,089
Tgal
TOTAL YEARLY COSTS $2,271,111
RECOMMENDED SAVINGS* $241,667 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $174,227

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings
01 2.1133: Adjust burners for efficient operation $81,353 $115,000 - - $81,353
-
MMBtu
- -
02 2.2511: Insulate bare equipment $50,015 $22,860 - - $50,015
-
MMBtu
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,425 $18,000 $17,036
327,624
kWh
$389
-
kW-mo/yr
- - -
04 2.2113: Repair or replace steam traps $92,874 $102,000 - - $74,466
-
MMBtu
$5,296
-
Tgal
$13,112
-
Tgal
TOTAL RECOMMENDED $241,667 $257,860 $17,036
327,624
kWh
$389
-
kW-mo/yr
$205,834
-
MMBtu
$5,296
-
Tgal
$13,112
-
Tgal
TOTAL IMPLEMENTED $174,227 $217,000 - - $155,819
-
MMBtu
$5,296
-
Tgal
$13,112
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs