Assessment Year | 2022 |
---|---|
Principal Product | PVC films and Laminates |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
140,177
ft2
|
Annual Production | 15,541,265
lb
|
Production Hrs. Annual | 8,424
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $514,602 | 11,948,341 |
kWh
|
$0.043 | |
Electricity Demand | $238,667 | 22,962 |
kW-mo/yr
|
$10.39 | |
Electricity Fees | $112,320 | - |
|
- | |
Natural Gas | $1,296,523 | 141,239 |
MMBtu
|
$9.18 | |
Waste Disposal Costs | |||||
Water Usage | $31,274 | 15,089 |
Tgal
|
$2.07 | |
Water Disposal | $77,725 | 15,089 |
Tgal
|
$5.15 | |
TOTAL YEARLY COSTS | $2,271,111 | ||||
RECOMMENDED SAVINGS* | $241,667 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $174,227 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $81,353 | $115,000 | - | - |
$81,353
-
MMBtu
|
- | - | |
02 | 2.2511: Insulate bare equipment | $50,015 | $22,860 | - | - |
$50,015
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,425 | $18,000 |
$17,036
327,624
kWh
|
$389
-
kW-mo/yr
|
- | - | - | |
04 | 2.2113: Repair or replace steam traps | $92,874 | $102,000 | - | - |
$74,466
-
MMBtu
|
$5,296
-
Tgal
|
$13,112
-
Tgal
|
|
TOTAL RECOMMENDED | $241,667 | $257,860 |
$17,036
327,624
kWh
|
$389
-
kW-mo/yr
|
$205,834
-
MMBtu
|
$5,296
-
Tgal
|
$13,112
-
Tgal
|
||
TOTAL IMPLEMENTED | $174,227 | $217,000 | - | - |
$155,819
-
MMBtu
|
$5,296
-
Tgal
|
$13,112
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs