Assessment Year | 2017 |
---|---|
Principal Product | Wholesale Plastics and finished Products |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2754: Commercial Printing, Gravure |
Sales Range | $100 M to 500M |
# of Employees | 80 |
Plant Area |
150,000
ft2
|
Annual Production | 10,000
units
|
Production Hrs. Annual | 4,300
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,229,910 | 13,134,266 |
kWh
|
$0.094 | |
Electricity Demand | $26,753 | 25,637 |
kW-mo/yr
|
$1.04 | |
Electricity Fees | $53,440 | - |
|
- | |
Natural Gas | $782,597 | 111,481 |
MMBtu
|
$7.02 | |
Waste Disposal Costs | |||||
Water Usage | $50,024 | 11,079,000 |
Tgal
|
$0.005 | |
TOTAL YEARLY COSTS | $2,142,724 | ||||
RECOMMENDED SAVINGS* | $78,994 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1212: Operate boilers on high fire setting | $16,174 | $28,750 | - |
$16,174
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $10,881 | $2,032 | - |
$10,881
-
MMBtu
|
|
03 | 2.2135: Repair and eliminate steam leaks | $12,079 | $3,000 |
$12,079
128,505
kWh
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $39,860 | $40,000 | - |
$39,860
-
MMBtu
|
|
TOTAL RECOMMENDED | $78,994 | $73,782 |
$12,079
128,505
kWh
|
$66,915
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs